Cost Estimate for Townhouses
Qty Craft @ Hours Unit Material Labor Equipment Total
-------------------------------------------------------------------------------------------------------------------------------------------------
FLOOR SLAB 4" thick
390721.00 B5@ 9377. SF 558,731.03 234,432.60 62,515.36 855,678.99
CRUSHED STONE
3/4" (Number 3)
4823.00 --@ .0000 Ton 53,053.00 0.00 0.00 53,053.00
EXTERIOR FOOTINGS
Footings and grade beams
24" W x 12" D (0.078 CY per LF)
30672.00 B4@ 4294. LF 174,523.68 106,125.12 58,890.24 339,539.04
Rebars in footings
1/2" diameter, #4 rebar (.67 lb per LF)
92016.00 RI@ 644.1 LF 16,562.88 15,642.72 0.00 32,205.60
Load Bearing Haunch
Typical cost per CY
1298.00 , B4@ 2336. CY 94,754.00 57,631.20 31,930.80 184,316.00
Rebars in Haunch
1/2" diameter, #4 rebar (.67 lb per LF)
64555.00 RI@ 451.9 LF 11,619.90 10,974.35 0.00 22,594.25
Patio
4" thick
10176.00 B5@ 244.2 SF 14,551.68 6,105.60 1,628.16 22,285.44
AD/2 Haunch
Typical cost per CY
3.00 B4@ 5.400 CY 219.00 133.20 73.80 426.00
Rebars in AD/2 Haunch
1/2" diameter, #4 rebar (.67 lb per LF)
80.00 RI@ .5600 LF 14.40 13.60 0.00 28.00
----------------------------------------------------------------------------------------------------------------------------------------------------
Totals:
Manhours Material Labor Equipment:
17354.0 24,029.57 431,058.39 155,038.36 1,510,126.32
Subtotal: 1,510,126.32
10.00% Overhead: 226,518.95
15.00% Profit: 260,496.79
Estimate Total: 1,997,142.06
Tax on Materials: 64,682.07
Tax on Equipment: 10,852.69
Grand Total: 2,072,676.82